Hey guys! I'm about 98% complete on my mod - and massive thanks to you all for the incredible knowledge base this site has been. I truly couldn't have done it without your help! =D>
So, my mod has taken me about about 12 days to complete, only working on the weekend days when it didn't rain. That puts it at about 120-140 hours! Whew!
I stressed out about the wiring and getting the correct wire gauges on several runs, as well as a few other minor things. Now I just have the last headache to go: mounting my new bow mount/foot controlled trolling motor.
The two 2x6s that I sealed and carpeted ended up being a bit too tall, and my idea around attaching it to the new decking doesn't seem to be sturdy enough (although I haven't attached it yet - the concept seems weak.) That's the only thing left to go besides a few fishing pole holders to install. Not exactly sure what I'll do about it, either.
Anyway, enjoy the pics!
And again, thank you so much for all of your help!
~Frani
So, my mod has taken me about about 12 days to complete, only working on the weekend days when it didn't rain. That puts it at about 120-140 hours! Whew!
I stressed out about the wiring and getting the correct wire gauges on several runs, as well as a few other minor things. Now I just have the last headache to go: mounting my new bow mount/foot controlled trolling motor.
The two 2x6s that I sealed and carpeted ended up being a bit too tall, and my idea around attaching it to the new decking doesn't seem to be sturdy enough (although I haven't attached it yet - the concept seems weak.) That's the only thing left to go besides a few fishing pole holders to install. Not exactly sure what I'll do about it, either.
Anyway, enjoy the pics!
And again, thank you so much for all of your help!
~Frani
Attachments
-
front_decking_support_2.jpg406.2 KB · Views: 10,778
-
wood_sealing.jpg575.1 KB · Views: 10,778
-
wood_sealing_2.jpg512.7 KB · Views: 10,778
-
dry_fit_wood.jpg332.5 KB · Views: 10,778
-
dry_fit_middle_section.jpg366.5 KB · Views: 10,778
-
carpeting.jpg495.9 KB · Views: 10,778
-
electrical_1.jpg467.7 KB · Views: 10,778
-
electrical_2.jpg420.6 KB · Views: 10,778
-
screwing_around.jpg336.9 KB · Views: 10,778
-
decking_1.jpg453.3 KB · Views: 10,778
-
decking_2.jpg503.8 KB · Views: 10,778